Bridgwater Tidal Barrier a Fatal Flaw

The existing Bridgwater Tidal Barrier scheme has a flaw.

Water can go  around it.

Any  system including a flood defence system is  only as good  as its weakest link. The banks of the River Parrett  is the  Achilles heal of the EA’s scheme.

The ground along the river is simply too weak to support the continued raising of the river banks and from the EA’s point of view  too expensive to maintain.  The Parrett’s highest tides hidden behind the  raised banks are already at the top of the doors of Bridgwater’s houses along the A38.

Even before it’s been built and the complete  scheme revealed to the public the  EA is working on adding secondary flood  banks (dashed red lines) on the premise of a bank failure  or  a future decision not to maintain the existing flood  defences. The drawing below is a scheme the EA has to fix the flaw.  The red arrow is the open back door at Walpol where a breach to the north could circumvent all the defences. When the Dutch build a dyke they don’t build another one a few hundred metres behind it; clearly the EA expects a failure to occur or the river to over top.

The line in green is an option never considered  by the EA but one that would offer much better protection than what is being proposed.

EA Secondary Flood Barrier, Downstream Bank Modifications and Alternative Barrier Route

This is information never presented to the public in any of the consultations in 2016.

To my knowledge Bridgwater will have the UK’s  only tidal surge barrier not located at the mouth of the river it’s meant to control. At Bridgwater’s present rate of expansion the proposed  barrier will in 100 years time not be just near the centre of Bridgwater but within  the centre of its developed area. Only in Somerset would anyone come up with  the plan we have and think its acceptable to have a scheme that has such an obvious flaw. Let’s also not forget that the EA’s other wider site downstream is being reserved for a road bridge to  land  that the EA is not  protecting in the same way as existing housing.  What happens when that is to be developed? Start again?

The ratepayer should have had real options presented rather than the EA’s version of  the Henry Ford motto “any colour you like as long as its black”, ie anywhere in the river as long as its at the narrowest part of the river we can persuade people to accept.

The letter below confirms that the barrier can be circumvented.

EA Letter to Chilton Trinity landowner

 

A Tidal Surge Barrier, A Bridge & Dunball Wharf

One of the problems with building the Bridgwater Tidal Barrier downstream of Dunball Wharf is the marine traffic to Dunball Wharf. Sedgemoor District Councils current draft local plan states “The Council will support the continued operation and potential development of Bridgwater Port including Dunball Wharf and Combwich Wharf (Policy D16 applies). It will also support the re-establishment of active commercial wharf’s at suitable locations elsewhere on the River Parrett. In all cases the construction or operation of new wharf’s should not adversely impact upon the Severn Estuary internationally designated site.”

The reality is that  the Dunball Wharf’s with their tidal drying berths, dependency on  high tides and difficult navigation is never going to be a commercial success but the 200m wide river at Combwich might. Construction of  the tidal surge barrier could enable the relocation of Dunball Wharf to a better location.

Much hangs on what is considered to be adverse.

Concepts of what the river structures might look like have not been forthcoming since 2009. Apart from the tower  and turning vertical gate Bridgwater’s gate structure will be considerably shorter than the Hull Barrier structure we have  been repeatedly shown.

What would a barrier with a road bridge  options look like?

Another wharf at Combwich, EDF have  one there already, would not require an opening bridge or clearance much more than Drove Bridge on the NDR. A tidal surge barrier with a 40m fixed navigation span and a road deck might look like

Keeping Dunball Wharf  would require a one larger gate and an opening bridge. Dunball currently sees 40 or so vessel movements a year so its operation would not affect the bypass traffic.

The engineering is relatively simple and with a purpose built wharf everything could be shipped in during construction.